Greenhouse Construction |
The plumbing and electrical conduits have been covered with a sand/clay mixture and compacted to specifications. Workers placed rigid polystyrene insulation around the inside perimeter of the headhouse wall and under the floor of the storage cooler. The cooler will provide postharvest storage of plant materials prior to shipping. The steel frame of the headhouse required a six-week fabrication notice. It was ordered in late October for delivery during the first week of December
|